Starting Monday, March 20, there will be weekly lane closures in Little Rock and North Little Rock as crews continue to work on Interstate 30.
Weather permitting, double-lane closures on interstate lanes will generally be limited to 11 p.m. to 4 a.m. Traffic will be controlled by construction barrels and signage. Drivers should exercise caution when approaching and traveling through all work zones.
Daytime closures (8 a.m. – 5 p.m.)
- I-30 frontage roads (single-lane closures) between 9th and 11th streets in Little Rock
- Riverfront Drive westbound (single-lane closure) between Pine and Cypress streets in North Little Rock
- 11th Street (full closure) at southbound I-30 frontage road in Little Rock
Overnight closures (8 p.m. – 5 a.m.)
- I-30 (single and double-lane closures and traffic shifts) between Roosevelt Road in Little Rock and I-40 in North Little Rock
- I-630 eastbound ramp to I-30 eastbound (full closure) in Little Rock; ramp detour signed to exit to the northbound frontage road
- I-30/I-40 lanes and ramps (single-lane closures) at the north terminal in North Little Rock
- I-30 frontage roads (single-lane closure) between 6th and 10th Streets in Little Rock
- 11th Street (full closure) at southbound I-30 frontage road in Little Rock
24-hour Closures
McGowan Street (full closure) between the on-ramp to I-30 westbound and Pulaski County Lane in Little Rock; the on-ramp to I-30 westbound is reduced to one lane; detours will be signed