Entergy Arkansas announced a second phase of its planned service for Google’s $4 billion data center in West Memphis.
The utility will invest in new infrastructure to strengthen the power grid for all Entergy Arkansas customers, according to a press release. The project is expected to generate at least $500 million in new customer savings starting in 2028 and extending over 20 years. This is in addition to a previously announced $1.6 billion identified in Entergy’s Fair Share Plus pledge from the first phase of Google’s West Memphis project, the release stated.
“Google is increasing its investment in West Memphis and building on the significant success of its first phase. We are delivering on our promise to all Entergy Arkansas customers to create value for everyone we serve by ensuring Google is not only paying 100 percent of its power needs but is also contributing to the existing grid and lowering the costs for everyone else,” said Laura Landreaux, president and CEO of Entergy Arkansas. “This partnership brings even more benefits to the West Memphis community. And our agreement with Google, which covers both the original and expansion project, aligns with Entergy’s Fair Share Plus pledge, and is expected to return more than $2.1 billion in savings back to our 738,000 customers while upgrading the infrastructure Arkansas needs for the future.”
The project will fulfill Google’s plan for data-center buildings on the site and accelerate the project timeline. The system resource upgrades will benefit all Entergy Arkansas customers and require approximately $600 million in planned investment and a power purchase agreement, both of which will be covered by Google, the release added.
This entails:
- A 1,000 megawatt-hour battery energy storage system at Driver Solar near Osceola, expected to be online in 2028.
- A 400 megawatt-hour battery energy storage system near Hot Springs, expected to be online in 2028.
- A 440 megawatt (ac) solar power purchase agreement from the Big Island solar facility being constructed in Mississippi County.
- Expansion of the Galet substation near West Memphis and construction of two new 230 kV transmission lines to serve the expanded data center campus.
READ ALSO: Hendrix to Grant Automatic Admission to Eagle Scouts and Gold Award Girl Scouts